Design Development Activities
Three core activities transform the client brief into an approved, production-ready design.
Activity Sequence
1. Concept Development (2-3 days)
↓
2. Material Selection (1-2 days)
↓
3. Design Approval (2 days)
Activities Overview
Concept Development
Duration: 2-3 days Owner: Creative Director Output: 3-5 concept sketches with annotations
Research character/period and create multiple design directions.
Material Selection
Duration: 1-2 days Owner: Creative Director (with Design Assistant support) Output: Material specifications with swatches and suppliers
Identify fabrics, trims, closures for each concept.
Design Approval
Duration: 2 days Owner: Creative Director Output: Client-signed approval with selected concept
Present concepts, gather feedback, finalize design.
Time Budget
| Activity | Minimum | Typical | Maximum |
|---|---|---|---|
| Concept Development | 2 days | 2.5 days | 3 days |
| Material Selection | 1 day | 1.5 days | 2 days |
| Design Approval | 1.5 days | 2 days | 2.5 days |
| Total Stage | 4.5 days | 6 days | 7.5 days |
Last Updated: 2026-02-02