Stage 1: Order Reception

Duration: 1 day Owner: Client Relations Manager Trigger: Client inquiry received (email, phone, or meeting request) Completion: Signed agreement with documented brief and timeline

Purpose

Capture all client requirements, set realistic expectations, and establish the foundation for a successful project.

Process Flow

Client Inquiry


Receive Brief ──────▶ Document Requirements
│ │
│ ▼
│ Assess Feasibility
│ │
▼ ▼
Estimate Timeline ◀─── Estimate Cost


Present Proposal ──────▶ Client Decision
│ │
▼ ▼
Sign Agreement [YES] Project Starts
[NO] Archive inquiry

Inputs

InputSourceRequired Information
Client InquiryClientContact info, event type, rough timeline
Character BriefClientCharacter description, reference images, event context
Budget RangeClientApproximate budget or price expectations

Activities

1. Receive Brief

Initial consultation to understand client needs.

Key Questions:

  • Who is the character?
  • What is the event (film, theatre, cosplay, etc.)?
  • When is the costume needed?
  • What is the approximate budget?
  • Any specific requirements (movement, durability, etc.)?

2. Timeline Estimation

Calculate realistic delivery timeline based on complexity.

Factors:

  • Design complexity (simple/moderate/complex)
  • Material availability
  • Current production queue
  • Special techniques required (armor, embroidery, etc.)

3. Client Communication

Present proposal and finalize agreement.

Deliverables:

  • Timeline estimate (best/typical/worst case)
  • Cost estimate (itemized)
  • Payment terms (deposit/milestones)
  • Communication plan (update frequency)

Outputs

OutputFormatDelivered To
Documented BriefPDF/NotionCreative Director
Timeline EstimateGantt chart or date rangesClient + Production Manager
Signed AgreementPDF contractClient + Finance

RABSIC Matrix

RolePositionSpecific Responsibility
A (Accountable)Client Relations ManagerOwns complete and accurate brief capture
R (Responsible)Client Relations ManagerConducts consultation, documents requirements
S (Support)Production AssistantSchedules meetings, prepares templates
C (Consulted)Creative DirectorAdvises on design feasibility
C (Consulted)Production ManagerAdvises on timeline feasibility
I (Informed)FinanceReceives signed agreement for invoicing

Quality Gate

Pass Criteria:

  • All brief questions answered
  • Client budget and timeline align with our capacity
  • Agreement signed by both parties
  • Brief document uploaded to project folder
  • Production Manager notified of new project

Failure Action: If requirements are unclear or infeasible, schedule follow-up consultation before proceeding.

Standard Operating Procedures

See SOPs for detailed step-by-step procedures:

Common Issues

IssueFrequencyMitigation
Vague character description40%Use standard questionnaire
Unrealistic timeline expectations30%Show example timelines early
Budget misalignment25%Present tiered options (basic/standard/premium)
Incomplete measurements20%Schedule dedicated measurement session

Success Metrics

  • Brief Completeness: Target >95% (all required fields filled)
  • Timeline Accuracy: Actual vs. estimated within ±2 days (target >80%)
  • Client Satisfaction: Agreement process satisfaction >9/10

Last Updated: 2026-02-02 Stage Owner: Client Relations Manager