Metric: Lead Time
Definition: Total calendar days from client inquiry to costume delivery
Target: 21 days (typical case) Range: 17-29 days
Lead Time Breakdown
Order Reception: 1 day (5%)
Design Development: 6 days (29%)
Pattern Making: 4 days (19%)
Production: 10 days (48%)
Delivery: 2 days (10%)
──────────────────────────────────
Total: 23 days (100%)
Lead Time Distribution
| Scenario | Days | Frequency | Drivers |
|---|---|---|---|
| Minimum | 17 | 10% | Simple design, standard materials, no revisions |
| Fast | 19-20 | 20% | Simple design, client quick to approve |
| Typical | 21-23 | 50% | Moderate complexity, one revision round |
| Slow | 24-26 | 15% | Complex design, material delays |
| Maximum | 27-29 | 5% | Major revisions, specialty materials |
Bottleneck Analysis
Most common delays occur at:
-
Design Approval (35% of delays)
- Client indecision adds 2-3 days
- Mitigation: Clearer concept presentation, guided decision-making
-
Material Sourcing (25% of delays)
- Specialty fabrics add 3-7 days
- Mitigation: Maintain inventory of common fabrics, identify backup options early
-
Production Embellishment (20% of delays)
- Complex beading/embroidery adds 2-5 days
- Mitigation: Better time estimation during design, schedule embellishment work earlier
-
Final Fitting Scheduling (15% of delays)
- Client unavailability adds 1-2 days
- Mitigation: Schedule fitting during production phase, not after
-
Pattern Revision (5% of delays)
- Fit issues add 1-2 days
- Mitigation: More thorough mockups for complex designs
Lead Time Improvement Targets
| Quarter | Target Average | Improvement Initiative |
|---|---|---|
| Q1 2026 | 21 days | Baseline measurement |
| Q2 2026 | 20 days | Reduce design approval delays |
| Q3 2026 | 19 days | Optimize material sourcing |
| Q4 2026 | 19 days | Maintain and refine |
Last Updated: 2026-02-02 Owner: Production Manager