Stage 2: Design Development

Duration: 5-7 days Owner: Creative Director Trigger: Approved brief from Order Reception Completion: Client-approved design with material specifications

Purpose

Transform client brief into concrete costume design with approved aesthetics, materials, and construction approach.

Process Flow

Approved Brief


Concept Development ──────▶ Research & Sketches
│ │
│ ▼
│ Material Selection
│ │
▼ ▼
Client Presentation ◀──── Prepare Lookbook


Client Review ──────▶ [APPROVED] ──────▶ Pattern Making Stage


[REVISE] ──────▶ Refinement (1-2 days) ──────▶ Re-present

Inputs

InputSourceRequired Information
Documented BriefClient Relations ManagerCharacter, event, requirements
Reference ImagesClientVisual inspiration
Timeline ConstraintsProduction ManagerAvailable time for design iteration
Budget ConstraintsClient Relations ManagerMaterial budget allocation

Activities

1. Concept Development (2-3 days)

Research character, period, and context. Develop 3-5 distinct concept directions.

Deliverable: Concept sketches showing silhouette, proportion, key details

2. Material Selection (1-2 days)

Identify fabrics, trims, closures, and special materials for each concept.

Deliverable: Material swatches, supplier info, cost estimates

3. Design Approval (2 days)

Present concepts to client, gather feedback, refine selected direction.

Deliverable: Client-approved final design with material list

Outputs

OutputFormatDelivered To
Final Design SketchesDigital (annotated)Pattern Maker
Material SpecificationsSpreadsheet + swatchesProduction Manager
Color PaletteDigital swatch cardProduction Manager
Construction NotesDocumentPattern Maker
Client ApprovalSigned approval formClient Relations Manager

RABSIC Matrix

RolePositionSpecific Responsibility
A (Accountable)Creative DirectorOwns design quality and client approval
R (Responsible)Creative DirectorCreates concepts, selects materials
S (Support)Design AssistantResearches references, prepares swatches
C (Consulted)Pattern MakerAdvises on construction feasibility
C (Consulted)ClientProvides feedback and final approval
I (Informed)Production ManagerReceives approved design for production planning

Quality Gate

Pass Criteria:

  • Client has signed design approval form
  • All materials identified with supplier and SKU
  • Color palette documented with Pantone or RGB values
  • Construction notes explain assembly approach
  • Budget still within client's approved range
  • Timeline still feasible for production

Failure Action: If client doesn't approve any concepts, conduct additional research round (adds 2-3 days to timeline).

Standard Operating Procedures

See SOPs for detailed procedures:

Common Issues

IssueFrequencyMitigation
Client loves parts of multiple concepts50%Offer hybrid concept combining elements
Material not available in needed quantity30%Identify 2-3 backup options during selection
Client requests major changes after approval20%Charge revision fee, explain timeline impact
Budget exceeded by material costs15%Present value-engineered alternatives

Revision Policy

Included:

  • Two rounds of concept revisions
  • Minor tweaks to approved design (color, trim, small details)

Additional Cost:

  • Third round of concepts: $150
  • Major changes after approval: $200 + timeline extension
  • Complete redesign: Restart design phase, additional 5-7 days

Success Metrics

  • First-Round Approval Rate: Target >60% (client approves one of initial concepts)
  • Total Revisions: Target \<2 rounds per project
  • Material Accuracy: Target >95% (materials as-specified are available)

Timeline Scenarios

ScenarioDurationTrigger
Simple Design5 daysModern costume, minimal research needed
Typical Design6 daysPeriod costume, moderate research
Complex Design7 daysIntricate details, extensive research
With Revision+1-2 daysClient requests changes
Major Redesign+5-7 daysClient rejects all concepts

Last Updated: 2026-02-02 Stage Owner: Creative Director