Step 2: Order Tracking

Duration: Ongoing throughout production (4-12 weeks typical) Owner: Account Manager Tool: Notion, Slack

Objective

Maintain continuous visibility into order status, proactively communicate with client, and coordinate cross-functional activities.

Inputs

  • Active order record in Notion
  • Production timeline from Operations
  • Design milestones from Fashion Design

Activities

1. Daily Status Monitoring (5 min/day)

Check Notion Order Tracker:

  • Current phase status (Design / Pattern / Construction / Fitting / Final)
  • Upcoming milestones and deadlines
  • Blockers or delays flagged by team
  • Client action items pending

Check Slack Project Channel:

  • Updates from Fashion Design or Operations
  • Material sourcing status
  • Any issues requiring Sales intervention

2. Weekly Client Updates (30 min/week)

Send Status Email Every Friday:

Subject: [Project Name] - Weekly Update

Hi [Client Name],

Here's your weekly progress update:

✅ Completed This Week:
- [Milestone 1: e.g., "Initial design sketches presented and approved"]
- [Milestone 2: e.g., "Fabric swatches selected"]

🔄 In Progress:
- [Activity: e.g., "Pattern making for lead character gown"]
- [Activity: e.g., "Sourcing embellishments for ball scene costumes"]

📅 Coming Up Next Week:
- [Milestone: e.g., "First fitting scheduled for Tuesday, Jan 23 at 2pm"]
- [Action needed: e.g., "Please confirm availability for fitting"]

We're on track for delivery on [Date]!

Let me know if you have any questions.

Best,
[Your Name]

Include:

  • Progress photos (if available and appropriate)
  • Timeline visual with current status highlighted
  • Any client decisions or inputs needed

3. Milestone Coordination (As needed)

Key Milestones Requiring Coordination:

Design Approval (Week 1-2)

  • Schedule client design review meeting
  • Present sketches and concepts
  • Document feedback and approvals in Notion
  • Update order status to next phase

Fabric Approval (Week 3-4)

  • Send fabric swatches or digital samples
  • Confirm material selections
  • Track fabric procurement timeline

First Fitting (Week 4-5)

  • Confirm client/actor availability
  • Coordinate with Fashion Design for mockup readiness
  • Schedule 2-hour fitting window
  • Document fit notes and required adjustments

Final Fitting (Week 7-8)

  • Schedule final fitting session
  • Coordinate any last-minute alterations
  • Get client sign-off on completed pieces
  • Confirm delivery logistics

4. Issue Management (As needed)

When Issues Arise:

Minor Issues (resolve immediately)

  • Fabric delivery delay (\<1 week impact)
  • Design tweak requests
  • Scheduling conflicts for fittings

Major Issues (escalate to Sales Director)

  • Timeline delays >1 week
  • Budget overruns >10%
  • Client dissatisfaction or scope disputes
  • Production quality concerns

Issue Resolution Protocol:

  1. Identify issue and impact (timeline, budget, quality)
  2. Consult with affected function (Design/Operations)
  3. Develop 2-3 solution options
  4. Present to client with recommendation
  5. Document decision and update timeline/scope
  6. Follow change order process if budget/scope changes

5. Change Order Management (As needed)

When Client Requests Scope Changes:

Evaluate Impact:

  • Design complexity change
  • Additional pieces or characters
  • Material upgrades
  • Timeline acceleration

Create Change Order:

  • Document requested changes
  • Get cost estimate from Finance
  • Get timeline impact from Operations
  • Calculate revised pricing

Get Approval:

  • Present change order to client with pricing and timeline impact
  • Require written approval (email or signed addendum)
  • Collect additional deposit if >20% cost increase
  • Update contract and Notion record

6. Payment Milestone Tracking (Ongoing)

Monitor Payment Schedule:

  • Deposit (50%): Due at contract signing
  • Mid-project (25%): Due after first fitting
  • Final (25%): Due at delivery

Payment Follow-Up:

  • Send invoice 3 days before milestone
  • Send reminder if payment not received by due date
  • Pause work if payment >7 days late (notify Sales Director)
  • Coordinate with Finance on collection if >14 days late

Outputs

  • Weekly client status updates
  • Up-to-date order status in Notion
  • Documented milestone approvals
  • Change orders processed (if any)
  • Payment milestones collected on schedule

Success Criteria

  • Client receives weekly updates (100% on-time)
  • No surprises - issues communicated within 24 hours of identification
  • All milestones met or delays communicated proactively
  • Client satisfaction maintained ≥4/5 throughout project

Communication Templates

Issue Notification Template

Subject: [Project Name] - Update on [Issue]

Hi [Client Name],

I wanted to give you a heads up on [issue description].

Situation: [What happened]
Impact: [How it affects timeline/budget/quality]
Our Plan: [How we're addressing it]

Options:
1. [Option 1: e.g., "Wait 1 week for original fabric, delivery moves to X"]
2. [Option 2: e.g., "Use alternative fabric, stay on schedule"]

Which option works better for your needs? I'm happy to discuss on a call if helpful.

Best,
[Your Name]

Change Order Approval Template

Subject: Change Order for [Project Name]

Hi [Client Name],

Per our conversation, here's the change order for:
[Description of requested changes]

Impact:
- Additional Cost: $[Amount] (itemized below)
- Timeline: [Impact on delivery date, if any]

Detailed Pricing:
- [Item 1]: $[Amount]
- [Item 2]: $[Amount]

To proceed, please reply confirming approval. We'll send an updated invoice
for the additional 50% deposit ($[Amount]) to begin work on these changes.

Let me know if you have any questions!

Best,
[Your Name]

Notion Fields to Update Regularly

Order Record:

  • Current Phase: [Design/Pattern/Construction/Fitting/Final]
  • % Complete: [Estimate based on milestones]
  • Last Client Update: [Date]
  • Next Milestone: [Description and date]
  • Blockers: [Any issues]
  • Change Orders: [Link to change order records]

Common Issues & Solutions

IssueSolution
Client unresponsive to update emailsCall directly, try different communication channel
Production behind scheduleAssess impact, communicate proactively, offer solutions (rush fee, phased delivery)
Client requests frequent changesSet expectation on change order process, document all changes
Payment delayedSend friendly reminder day 5, firm reminder day 7, pause work day 8
Client unhappy with design directionSchedule immediate review call, present alternatives, loop in Lead Designer

Next Step

Step 3: Order Closure